GAM · Optimal Order Quantity — Strategy & Tricks

One square root, five one-liners, and the six slips the wrong options are built to catch. · 13 min read

⬇ Download this guide as a PDF

📐 One formula, five cousins

Order too often and you drown in paperwork; order too rarely and you drown in stock. The Economic Order Quantity is the lot size where the annual ordering bill equals the annual holding bill — the point where their sum is smallest. Everything here flows from it and a few one-liners.

Exam facts About 60 questions in 90 minutes — roughly 90 seconds each — one passage shared by four or five questions, four options, no negative marking. Never leave a blank. No calculator; the passage states the model it wants.
Q* = √(2DS ÷ H) — optimal order size
N = D ÷ Q — orders per year
Ordering cost = (D ÷ Q) × S
Holding cost = (Q ÷ 2) × H — average stock is Q ÷ 2
At Q*: ordering cost = holding cost
TC* = √(2DSH) = Q* × H — minimum relevant cost
d = D ÷ working days (360, 250 or 365 — as stated)
ROP = d × L (+ safety stock SS)
Cycle = Q ÷ d = working days ÷ N
D annual demand · S per order · H per unit-year · Q order size · N orders a year · d daily demand · L lead time · SS safety stock. Passages may say A, O, C.

Not in the kit: the purchase price. With a fixed unit price the annual purchase bill is fixed too, so it cannot move Q. It enters only with a quantity discount, where you compare full* annual cost at each break.

Why a square root Ordering cost (D ÷ Q) × S falls as Q grows; holding cost (Q ÷ 2) × H rises. The sum bottoms out where they meet, and setting them equal gives Q² = 2DS ÷ H — so at the optimum one cost gives you both.

👀 Sort it in five seconds

Every question here is one of six jobs. Name the job before you touch a number.

JobSounds likeDo thisBudget
Compute Q*'the EOQ is…'√(2DS ÷ H); make the inside a perfect square40–50 s
Cost at a given Q'orders 1,500 at a time'That Q: (D ÷ Q) × S and (Q ÷ 2) × H separately45–60 s
Timing'reorder point', 'days between orders'd first; then d × L + SS, or days ÷ N45–60 s
Proportional change'D rises 44%, H falls 36%'Ratio inside the root, never a fresh sum30–45 s
Reverse-engineer'the reported EOQ is 1,200'Square it: S = HQ² ÷ 2D, H = 2DS ÷ Q², D = HQ² ÷ 2S50–60 s
Compare policies'Q = 600 or Q = 1,000?'Relevant cost at each; the curve is flat near Q*70–90 s

Optimal means the costs are equal, so do one. A Q handed to you means do both.

Linked questions share the passage With Q*, N and d in hand, every other question in the set is one multiplication: the first is expensive, the rest are the reward.

🧠 Label the givens, then move

Before any formula, write six labels in the margin and fill in what the passage gives. A blank is information too — it tells you which variant you're in.

  1. D — demand per year: 1,500 a month → 18,000; a 900-unit lot lasting 3 months → 3,600.
  2. S — cost per order, not a year's worth.
  3. H — holding cost per unit per year. A percentage of price? Multiply: 10% of 40 = 4.
  4. Q — is one given? Yes: cost that Q. No: compute Q* = √(2DS ÷ H).
  5. L, SS, days — lead time, safety stock, working-day year (360, 250 or 365).
  6. Write N = D ÷ Q and d = D ÷ days beside Q; later questions are then one line.
  7. Answer exactly what was asked — Q*, one cost, N, days, ROP — then stop.
A workshop uses 500 units a month. An order costs 30, and holding a unit for a year costs 10% of its 40 price. Deliveries arrive 6 working days after ordering; the shop works 250 days a year and keeps 150 units in reserve. Use Q* = √(2DS ÷ H) and ROP = d × L + SS.
Labelled: D = 6,000 · S = 30 · H = 4 · L = 6 · SS = 150 · 250 days.

Labelling buys the whole set: Q* = √(2 × 6,000 × 30 ÷ 4) = √90,000 = 300; N = 20; d = 24; ROP = 24 × 6 + 150 = 294; cycle = 300 ÷ 24 = 12.5 days.

In a table, each row is its own EOQ: take the row the stem names and read units off the headings.

ItemD (units/year)S (per order)H (per unit-year)
P-109,000204
P-2018,000303
P-3024,000503

✂️ Roots without a calculator

No calculator, and the setters know it: the number under the root is nearly always a perfect square in disguise.

Perfect-square radar 11² = 121, 12² = 144, 13² = 169, 14² = 196, 15² = 225, 16² = 256, 25² = 625 — and the percentage versions 1.21, 1.44, 1.69, 0.49, 0.64, 0.81. See one, the root is instant.

⚡ The 90-second budget

Ninety seconds is the average, not the ration: a five-question set gets about seven minutes, front-loaded.

PhaseSecondsWhat happens
Read and label20–25Six labels; months to years, percentages to H.
First question (usually Q*)30–40Cancel, root, pick; write Q*, N and d down.
Each linked question20–40One multiplication or one ratio.
Sanity check5Costs at Q equal? ROP below Q? N × Q ≈ D?
When the root won't resolve √800,000 sits between 800² = 640,000 and 900² = 810,000, close to the top — about 894. Bracket it, take the nearest option, move on.

That is the exact-versus-estimate line: a clean square is exact, anything else you bracket.

🪤 Six ways to lose a free mark

Nothing here is hard; everything is easy to get wrong at speed, and each trap has an option waiting.

  1. A given Q is not optimal. 'Orders 1,000 at a time' does not equalise the costs — do both; the trap option doubles one.
  2. Per unit-month vs per unit-year. 0.50 a month becomes 6 a year. '15% of unit price' means multiply, not plug in 0.15.
  3. Monthly demand under the root. The answer lands √12 ≈ 3.5 times too small — always an option.
  4. Units vs orders. Q is units; N = D ÷ Q is orders — the commonest mis-read here.
  5. Safety stock forgotten — or added twice. ROP = d × L + SS, once; average stock with a reserve is Q ÷ 2 + SS, once.
  6. The wrong year. Daily demand uses the year the passage states; switch it and every ROP option looks plausible.
What to avoid Don't improve the passage's conventions. If it says 360 days, use 360. The options were written from the setter's assumption, not yours.

🧩 Worked examples, easy to hard

Six passages built like real items — cover the steps, then compare.

easyStraight EOQtarget 45s

The optimal order quantity is:

A wholesaler sells 9,000 cartons a year at a steady rate. An order costs 20; holding a carton for a year costs 4. Use Q* = √(2DS ÷ H).
  1. 212 cartons
  2. 300 cartons
  3. 600 cartons
  4. 1,200 cartons
Show the answer and the steps
  1. Label: D = 9,000, S = 20, H = 4. No Q given, so compute Q*.
  2. Cancel: 2 × 20 ÷ 4 = 10, so 2DS ÷ H = 9,000 × 10 = 90,000.
  3. √90,000 = √9 × √10,000 = 3 × 100 = 300.
  4. Traps: 212 = √45,000 (the 2 dropped); 600 doubles it; 1,200 multiplies by H.

Answer: 300 cartons

easyOrders and cycle lengthtarget 60s

At the EOQ, how many days pass between consecutive orders?

A garden centre uses 8,000 bags of compost a year over a 360-day trading year, orders evenly spaced. Ordering costs 40; holding 4 per bag a year. Use Q* = √(2DS ÷ H).
  1. 9 days
  2. 18 days
  3. 20 days
  4. 36 days
Show the answer and the steps
  1. Label: D = 8,000, S = 40, H = 4, year = 360 days.
  2. Q* = √(2 × 8,000 × 40 ÷ 4) = √160,000 = 400 bags, so N = 8,000 ÷ 400 = 20 orders and the cycle is 360 ÷ 20 = 18 days.
  3. Check: d ≈ 22.2 a day, and 400 ÷ 22.2 ≈ 18.
  4. Traps: 20 is the order count; 9 means lots of 200, 36 lots of 800.

Answer: 18 days

mediumCost at a lot size that isn't optimaltarget 75s

The total relevant annual inventory cost of this policy is:

A distributor needs 24,000 units a year. Ordering costs 50 per order, holding 3 per unit-year; total relevant annual cost is (D ÷ Q) × S + (Q ÷ 2) × H. For handling reasons it orders lots of 1,000.
  1. 2,400
  2. 2,700
  3. 3,000
  4. 4,200
Show the answer and the steps
  1. Label: D = 24,000, S = 50, H = 3, Q = 1,000 — given, so the two costs will not be equal.
  2. Ordering: (24,000 ÷ 1,000) × 50 = 24 × 50 = 1,200.
  3. Holding: (1,000 ÷ 2) × 3 = 500 × 3 = 1,500.
  4. Total = 1,200 + 1,500 = 2,700.
  5. Traps: 2,400 and 3,000 double one component, as if Q were optimal; 4,200 forgets the ÷ 2.

Answer: 2,700

mediumMonthly demand and a percentage holding costtarget 75s

The economic order quantity is closest to:

A retailer sells 1,500 units a month. The unit costs 20, and holding cost is 15% of unit cost per year. An order costs 30 to place. Use Q* = √(2DS ÷ H), with D the annual demand.
  1. 173 units
  2. 232 units
  3. 600 units
  4. 2,683 units
Show the answer and the steps
  1. Convert: D = 1,500 × 12 = 18,000 a year; H = 15% × 20 = 3 per unit-year; S = 30.
  2. Cancel: 2 × 30 ÷ 3 = 20, so 2DS ÷ H = 18,000 × 20 = 360,000.
  3. √360,000 = 6 × 100 = 600.
  4. Traps: 173 uses monthly demand, 232 the price 20 as H, 2,683 the bare 0.15.

Answer: 600 units

hardTwo things change at oncetarget 60s

The new EOQ is:

Under Q* = √(2DS ÷ H), a distributor's EOQ is 1,200 units on annual demand of 36,000 units and holding cost 5 per unit-year. Demand is forecast to rise 44% and holding cost to fall 36%. Ordering cost is unchanged.
  1. 1,440 units
  2. 1,500 units
  3. 1,800 units
  4. 2,700 units
Show the answer and the steps
  1. You never need S. Q scales with √(D ÷ H), so new Q = 1,200 × √(1.44 ÷ 0.64).
  2. √1.44 = 1.2 and √0.64 = 0.8; 1.2 ÷ 0.8 = 1.5, so 1,200 × 1.5 = 1,800.
  3. Check: S = HQ² ÷ 2D = 100; then D = 51,840 and H = 3.2 give 2DS ÷ H = 3,240,000, root 1,800.
  4. Traps: 1,440 is the demand factor alone, 1,500 the holding factor alone, 2,700 skips the root.

Answer: 1,800 units

hardForced lot sizes and the penaltytarget 90s

Comparing the two feasible lots with the theoretical minimum cost:

A factory uses 20,000 components a year. An order costs 100; holding one component for a year costs 4. Relevant annual cost is (D ÷ Q) × S + (Q ÷ 2) × H, minimised at Q* = √(2DS ÷ H). The supplier ships only lots of 500 or 2,000.
  1. 500 is cheaper, 25% above the minimum
  2. 2,000 is cheaper, 25% above the minimum
  3. Both the same, 25% above the minimum
  4. Both the same, 12.5% above the minimum
Show the answer and the steps
  1. Q = √(2 × 20,000 × 100 ÷ 4) = √1,000,000 = 1,000, so TC = Q* × H = 4,000.
  2. Q = 500: ordering 40 × 100 = 4,000, holding 250 × 4 = 1,000, total 5,000.
  3. Q = 2,000: ordering 10 × 100 = 1,000, holding 1,000 × 4 = 4,000, total 5,000.
  4. Both give 5,000 ÷ 4,000 = 1.25 — the 25% the ratio rule predicts at half or double the EOQ. A tie, so any 'cheaper' option is out; 12.5% is that halved.

Answer: Both the same, 25% above the minimum

Go Zero to dMAT

Strategy is the map; volume under the clock is the journey — 2,858 questions and 15 timed papers, the reasoning drawn on every one.

Start practising — free during launch (₹799 → ₹0)

🎯 Recognition drills

Recognition is the speed, not arithmetic. Say each answer out loud before the seconds run out.

Which line of the kit?

Name the formula, not the number.

  1. 'How many orders per year at the EOQ?'5s
    Answer

    N = D ÷ Q*

  2. 'Average cycle inventory for lots of 900?'5s
    Answer

    Q ÷ 2 = 450 — the given Q, not Q*

  3. 'At what stock level does a new order go out?'6s
    Answer

    ROP = d × L + SS

  4. 'Minimum total relevant annual cost?'6s
    Answer

    √(2DSH), or Q* × H

  5. 'Using a 250-day year, time between orders?'6s
    Answer

    250 ÷ N (or Q ÷ d)

  6. 'Reported EOQ 800; the implied ordering cost?'8s
    Answer

    S = H × Q² ÷ 2D

  7. '2% off for lots of 2,000 or more — switch?'8s
    Answer

    Full annual cost at 2,000 vs at Q*

Roots and ratios, no pen

Mental arithmetic only.

  1. √1,440,0005s
    Answer

    1,200

  2. √(2 × 12,000 × 15 ÷ 4)10s
    Answer

    √90,000 = 300

  3. √(2 × 25,000 × 80 ÷ 4)10s
    Answer

    √1,000,000 = 1,000

  4. D up 69%: Q* factor?6s
    Answer

    √1.69 = 1.3

  5. H up 25%: Q* factor?8s
    Answer

    1 ÷ √1.25 ≈ 0.89

  6. S down 51%: Q* factor?6s
    Answer

    √0.49 = 0.7

  7. D doubles and H doubles: Q* factor?5s
    Answer

    1 — unchanged

  8. Q = 1,250 when Q* = 1,000: cost penalty?10s
    Answer

    0.5 × (1.25 + 0.8) = 1.025, so 2.5%

Spot the conversion

Each prompt hides one conversion — state it.

  1. Demand 2,000 units per month4s
    Answer

    D = 24,000 per year

  2. Holding cost 10% of a 30 unit price5s
    Answer

    H = 3 per unit-year

  3. Carrying cost 0.50 per unit per month5s
    Answer

    H = 6 per unit-year

  4. 900 units per lot; one lot lasts 3 months6s
    Answer

    D = 3,600 per year

  5. D = 10,000, 250 working days, lead time 5 days8s
    Answer

    d = 40; lead-time demand 200

  6. 15 orders a year of 2,400 units each5s
    Answer

    D = 36,000 per year

  7. Reorder level 600 including 100 safety stock5s
    Answer

    Lead-time demand = 500

🧭 Guided walk-through: one passage, four questions

A components stockist sells 15,000 units a year over 250 working days. An order costs 48; holding a unit for a year costs 4. Delivery takes 5 working days, and the stockist holds 120 units of safety stock. Use Q* = √(2DS ÷ H), ROP = d × L + SS, and relevant cost = (D ÷ Q) × S + (Q ÷ 2) × H.
Four questions: EOQ, orders per year, reorder point, cost of lots of 1,000.
  1. 0:00–0:20 — Label. D = 15,000, S = 48, H = 4, days = 250, L = 5, SS = 120. Q = 1,000 appears only in Q4.
  2. 0:20–0:50 — Q1, the EOQ. 2 × 48 ÷ 4 = 24; 15,000 × 24 = 360,000; √360,000 = 600.
  3. 0:50–1:05 — Q2, orders a year. N = 15,000 ÷ 600 = 25; bonus, cycle = 250 ÷ 25 = 10 days.
  4. 1:05–1:35 — Q3, reorder point. d = 15,000 ÷ 250 = 60; lead-time demand 60 × 5 = 300; ROP = 420. A 300 option forgets the reserve; 540 counts it twice.
  5. 1:35–2:20 — Q4, cost at Q = 1,000. Not optimal, so both: ordering 15 × 48 = 720, holding 500 × 4 = 2,000, total 2,720. At Q* it would be 600 × 4 = 2,400, so a higher figure is right.
  6. 2:20 — Done. Four questions in 140 seconds against a budget of 360.
Notice the order of work Q first, then N and d, and every later question is one line. If a set opens with a reorder-point question, label everything first anyway — d never needed Q.

📈 Progressive practice

Three untimed sets. Accuracy first — make each variant automatic before you race it.

Easy — compute Q*, N, average stock, one cost at Q* → 6 real easy questions · free, no login

Easy: D, S and H given, one line of the kit. Move on at 6 of 6.

Medium — given Q, conversions, percentage changes, two-policy comparisons → 6 real medium questions · free, no login

Medium: a hidden conversion, or a Q that isn't optimal. Move on at 5 of 6.

Hard — reverse-engineering, ROP with safety stock, cost penalties, discounts → 6 real hard questions · free, no login

Hard: two ideas chained — the hidden S, then a rescale. Move on at 4 of 6.

⏱️ Speed training

Now the clock, with targets from the budget table. Log where the seconds go: reading, labelling or the root.

Easy under 45 s each → 6 real easy questions, against the clock · free, no login

Medium under 75 s each → 6 real medium questions, against the clock · free, no login

Hard under 90 s each → 6 real hard questions, against the clock · free, no login

🏆 Exam application

This family arrives as one passage with four or five linked questions. Treat the set as a unit: budget six to seven minutes, the first on labels and Q*.

Exam simulation — 90 s per question, options only → 6 real hard questions, against the clock · free, no login

The last ten seconds of every set Costs at Q equal? ROP below Q? N × Q ≈ D? D in units per year? Four checks, one glance, several marks.

📋 Cheat sheet

Q* = √(2DS ÷ H)
N = D ÷ Q · Cycle = working days ÷ N = Q ÷ d
Ordering = (D ÷ Q) × S · Holding = (Q ÷ 2) × H
At Q*: ordering = holding · TC* = √(2DSH) = Q* × H
Average stock = Q ÷ 2 (+ SS if a reserve is held)
d = D ÷ working days (as stated) · ROP = d × L + SS
Reverse: S = HQ² ÷ 2D · H = 2DS ÷ Q² · D = HQ² ÷ 2S
Scaling: Q* ∝ √D, √S, 1 ÷ √H · D × 4 → Q* × 2
Penalty: 0.5 × (Q ÷ Q* + Q* ÷ Q) · half or double → +25%
Write these from memory in 60 seconds.

Go Zero to dMAT

Strategy is the map; volume under the clock is the journey — 2,858 questions and 15 timed papers, the reasoning drawn on every one.

Start practising — free during launch (₹799 → ₹0)

Every example here is original, written to the dMAT's mechanisms and designed with the official sample tasks in mind — nothing is copied from g.a.s.t.'s materials. dMAT.practice is an independent study aid by NinjaMinds Software Solutions, not connected to g.a.s.t., APS India or any university; use the official practice materials alongside it.